Package On this project we were required to pour ground floor slabs and First floor slabs on Metal deck flooring to four units. We have managed to pour all slabs to 4 separate units totalling to 2500 m2 with power floor finish in just two pours
Contract Value
£120K
Principal Contractor
Stainforth Construction LLP
Concrete Poured
300 m3